Tariff of Fees Bylaw

Development Charges Bylaw

Processing of Building permits varies depending on the project type.  The Ontario Bulding Code stipulates timelines for permit issuance.  The list provided below is only a guideline for residential proejcts.  The times indicated do not include the day that the permit was dropped off, day 1 starts the next business day. 

Note that the procesing timelines commence after all the required information is received in our office to issue the permit.
  • Single Family Dwelling (SFD) - 10 Business Days
  • House Addition/Renovation - 10 Business Days
  • Pools/Decks/Fences - 10 Business Days
  • Shed/Garage/Pole Barn - 10 Business Days
  • Commercial, Industrial, Institutional - Please call the office for timeframes
Date edited: 01/28/2018